Difference between revisions of "Sponsored Development: Libero Costing Engine"
From ADempiere
This Wiki is read-only for reference purposes to avoid broken links.
(→Development & Consulting) |
(→FAQ) |
||
Line 224: | Line 224: | ||
===Entity Relationship Model=== | ===Entity Relationship Model=== | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
[[Category:LIBERO]] | [[Category:LIBERO]] |
Revision as of 10:03, 6 May 2010
Contents
Project
Sponsored
Development & Consulting
Roadmap Document
Functionality / Feature | Status | Developer | Priority | Milestone | Release Date | Summary |
---|---|---|---|---|---|---|
Performance Analysis -> Costing -> Cost Engine | ||||||
Implement method in parallel | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
* Implement cost method by organization | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
* Implement cost layer and history | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
Material Management | ||||||
Inventory revaluation (all methods) | Under development | Teo Sarca | High | 354 | 2010/05/31 | ... |
Inventory reports | Under development | Teo Sarca | High | 354 | 2010/05/31 | ... |
Performance Analysis -> Costing -> Average Costing Method | ||||||
Implement to Average Cost fix when an user entry the data error | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
Implement the layer to solve the reverse documents | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
Implement the Average cost to Manufacturing functionality | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
Review and fix the current algoritm | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
Performance Analysis -> Costing -> FIFO/LIFO Costing Method | ||||||
Separate the Policy Material of FIFO/LIFO Cost | Under development | Teo Sarca | High | 354 | 2010/05/31 | ... |
Review and fix the current algoritm | Under development | Teo Sarca | High | 354 | 2010/05/31 | ... |
Performance Analysis -> Costing -> Standard Costing Method | ||||||
Implement the frozen/unfrozen Cost | Under development | Victor Perez | High | 354 | 2010/05/31 | ... |
Roles
- Analyst
- Any Role
- Architect
- Developer
- Project Manager
- Stakeholder
- Tester
Tasks
Develop Vision
[Document Specification]
Identify Stakeholders Ok
- Warehouse Clerk
- Accountant Cost Clerk
- Financial Management Clerk
- Purchase Manager Clerk
- Implementor Clerk
Gain agreement on the problem to resolve
- You can not give to tracking and monitoring the costs for any costing method. ie currently you can not generated a valuation of inventories at a effective date.
- All documents reverted with cost are created with accounting incorrectly.
- In the average cost is not possible to process correction of incorrect entry of quantities or prices
- Can not generate of transaction cost accounting for any revaluation or change cost.
- Only is possible to management a method costing by company or organization.
- The FIFO/LIFO costs, currently not working properly.
- Currently is not possible to have different method cost by organization
- Currently is not possible have a good historial cost for all method cost
Also add some new functionality.
- Development the functionality that support manufacturing support Average and FIFO/LIFO cost.
- Allow that the ADempiere support different costing method by organization, this way a organization can have the average cost and the other is standard cost.
- New Inventory report valuation
- Revaluation Cost
- COGS Adjustment
Gather stakeholder requests
- Optimize the Calculated Cost
- Optimize the Calculated Sales Price based on % margin
- Optimize the Right General Ledger record
- Optimize the Right Record the COGs for Income Statement
- Optimize the Right inventory valuation with different method cost
Define the scope of the solution
The objectives to reach within the first milestone of the project are:
- Create New Cost Engine
- Get the right calculated and register of cost
- Implement Average Cost and FIFO/LIFO Cost for Manufacturing Management
- Get the right the inventory valuation
- Get the right general leder cost records
- Ger the right current cost for each cost element
Define features of the system
- Define Multiples Cost Element with different Cost Method
- New Inventory Valuation Report
- New cost collector cost for cost adjustment and revaluation
- New option to generate the posting in batch process
- New option to generate the adjustment cost in batch process
- New transaction valuation report
Important questions
Achieve concurrence
Capture a common vocabulary
- Glossary