Difference between revisions of "Libero Manual"

From ADempiere
Jump to: navigation, search
This Wiki is read-only for reference purposes to avoid broken links.
m (User Manual)
m (User Manual)
 
(18 intermediate revisions by 3 users not shown)
Line 1: Line 1:
this is an in-progress task.. pls do not edit. thanks! -- [[User:Red1|Red1]] 22:40, 19 December 2006 (EST)
 
 
==User Manual==
 
==User Manual==
A Manufacturing Resource is defined as anything required for production and a deficiency of availability to  cause  not to reach the Production Plan. The Manufacturing Resources can be: Plants, Production lines, Work Centers and Work Stations.
 
  
It mainly answer the question: Where is the product made?
+
This Manual is sponsored by e-Evolution, written By Miguel Jimenez [mailto:miguel.jimenez@e-evolution.com].
  
===Manufacturing Rules===
+
Libero is sponsored by [http://www.e-evolution.com e-Evolution], developed by Victor Perez [mailto:victor.perez@e-evolution.com].
The Resource Type Window is the Compiere standard option which it is used to calculate the available time in a resource. It allows to enter the starting time and the end time for the slot in  the working days.   For more information please see the Chapter 16 of the Compiere User Manual.  
+
  
[[Image:Libero1.png]]
+
To improve this manual , please contact [[User:Red1|Redhuan D. Oon]] or other editors in the history page.
  
 +
===Manufacturing Rules===
 
===Manufacturing Resource Management===
 
===Manufacturing Resource Management===
To enter a Manufacturing Resource double-click in  Manufacturing < Manufacturing Rules <Manufacturing Resource Management  < Manufacturing Resource.  
+
A '''Manufacturing Resource''' is defined as anything required for production and its unavailability can affect the Production Plan. Manufacturing Resources can be: ''Plants, Production lines, Work Centers'' and ''Work Stations''.
 +
 
 +
It mainly answers the question: Where is the product made?
  
The Manufacturing Resource defines a resource for an Organization. You can introduce as many resources as you wish. 
 
 
====Resource Type====
 
====Resource Type====
 +
The '''Resource Type Window''' is the ADempiere standard option which it is used to calculate the available time in a resource. It allows input of ''starting time'' and ''end time'' for the slot according to the working days.  For more information please look in the [[Manual|Reference Manual]].
 +
 +
[[Image:Libero1.png]]
 +
 +
Figure 1.1.1.1
 +
 
====Manufacturing Resource====
 
====Manufacturing Resource====
===Manufacturing Workflows===
+
To enter a Manufacturing Resource double-click in 
====Manufacturing Workflows====
+
*Manufacturing
====Work Flow Editor====
+
**Manufacturing Rules
====Bills of Material & Formula====
+
***Manufacturing Resource Management
====Bills of Material &Formula====
+
****Manufacturing Resource.
====Bill Of Material & Formula review====
+
 
===Data Planning====
+
The Manufacturing Resource defines a resource for an Organization. You can introduce as many resources as you wish.  
====Planning Products====
+
 
====Create Product planning====
+
[[Image:Libero2.png]]
===MRP (Requirement Planning of Materials)===
+
 
====Calculate low level====
+
Figure 1.1.1.2
====Create record MRP====
+
 
====Re-Generate Material Plan====
+
The ''Resource Type'' field allows you to identify the capacity for this resource.
====MRP Detail Review====
+
 
====Action Messages====
+
When you tick the ''Is Manufacturing Resource'' check box the next fields are shown: ''Manufacturing Resource Type, Daily Capacity,  Percent Utilization, Queuing Time'' and ''Waiting Time''.
====Capacity Requirement Planning====
+
 
====Capacity Plan Calculation====
+
In the ''Manufacturing Resource Type'' field you can select a '''Resource''' among ''Work station, Production Line, Work Center'' or ''Plant''. Normally a group of work stations  will be integrated into a  work center,  a group of work centers in a Production line and a group of production lines in a '''Plant'''. This relation is build in a hierarchy which is used to accumulate the required and available capacity since the lower to the upper hierarchies for each resource.
====Resource Load View 29====
+
 
===Discrete Manufacturing===
+
The ''Utilization Percent'' for a resource is defined as the required time for that resource divided by the available time, the result is multiplied by 100.
====Planned Order Approval====
+
 
====Manufacturing Order====
+
The ''Queue Time'' is the time which normally a manufacturing order  operation  has to wait since it is moved to this operation until it starts to be worked. The ''Waiting Time'' is the time which normally a manufacturing order  operation  has to wait since it is finished until it is moved to the next operation or to the warehouse. Both, queue time and waiting time entered in the resource are used as default values for the nodes in the workflow.
====Manufacturing Orders Report====
+
 
====Component Check====
+
[[Image:Libero3.png]]
====Order Transactions====
+
 
====Printing and Release Order====
+
Figure 1.1.1.3
====Order Receipt and Issue====
+
 
 +
The Resource Window is opened with the menu option
 +
*Partner Relations
 +
**Service
 +
***Resource
 +
you can enter ''holidays'', the ''planned cost'' etc. as you need. For more information on Resource please refer to  Compiere User Manual 252d  Chapter 16. Service
 +
 
 +
The available daily time will be calculated for every weekly working day selected,  when you tick the ''Day Slot''. The calculation to get the available time for a day substracts the time when the slot starts, from the time when the slot ends.
 +
 
 +
===[[Manufacturing Workflows]]===
 +
===[[Production Planning]]===
 +
====[[Capacity Requirement Planning]]====
 +
===[[Production Control]]===
 +
===[[Cost Group]]===
 +
 
 +
==Links==
 +
*Back to [[Libero]]
 +
 
 +
==See Also==
 +
*[[Sponsored Development: Libero Manufacturing Work Shop]]
  
==Cost Group==
+
[[Category:Documentation]]
==Create Cost Element==
+
[[Category:LIBERO]]
==Create Element==
+
==Product Cost==
+
==Product Costing Report==
+
==Cost Collector==
+

Latest revision as of 16:18, 20 February 2011

User Manual

This Manual is sponsored by e-Evolution, written By Miguel Jimenez [1].

Libero is sponsored by e-Evolution, developed by Victor Perez [2].

To improve this manual , please contact Redhuan D. Oon or other editors in the history page.

Manufacturing Rules

Manufacturing Resource Management

A Manufacturing Resource is defined as anything required for production and its unavailability can affect the Production Plan. Manufacturing Resources can be: Plants, Production lines, Work Centers and Work Stations.

It mainly answers the question: Where is the product made?

Resource Type

The Resource Type Window is the ADempiere standard option which it is used to calculate the available time in a resource. It allows input of starting time and end time for the slot according to the working days. For more information please look in the Reference Manual.

Libero1.png

Figure 1.1.1.1

Manufacturing Resource

To enter a Manufacturing Resource double-click in

  • Manufacturing
    • Manufacturing Rules
      • Manufacturing Resource Management
        • Manufacturing Resource.

The Manufacturing Resource defines a resource for an Organization. You can introduce as many resources as you wish.

Libero2.png

Figure 1.1.1.2

The Resource Type field allows you to identify the capacity for this resource.

When you tick the Is Manufacturing Resource check box the next fields are shown: Manufacturing Resource Type, Daily Capacity, Percent Utilization, Queuing Time and Waiting Time.

In the Manufacturing Resource Type field you can select a Resource among Work station, Production Line, Work Center or Plant. Normally a group of work stations will be integrated into a work center, a group of work centers in a Production line and a group of production lines in a Plant. This relation is build in a hierarchy which is used to accumulate the required and available capacity since the lower to the upper hierarchies for each resource.

The Utilization Percent for a resource is defined as the required time for that resource divided by the available time, the result is multiplied by 100.

The Queue Time is the time which normally a manufacturing order operation has to wait since it is moved to this operation until it starts to be worked. The Waiting Time is the time which normally a manufacturing order operation has to wait since it is finished until it is moved to the next operation or to the warehouse. Both, queue time and waiting time entered in the resource are used as default values for the nodes in the workflow.

Libero3.png

Figure 1.1.1.3

The Resource Window is opened with the menu option

  • Partner Relations
    • Service
      • Resource

you can enter holidays, the planned cost etc. as you need. For more information on Resource please refer to Compiere User Manual 252d Chapter 16. Service

The available daily time will be calculated for every weekly working day selected, when you tick the Day Slot. The calculation to get the available time for a day substracts the time when the slot starts, from the time when the slot ends.

Manufacturing Workflows

Production Planning

Capacity Requirement Planning

Production Control

Cost Group

Links

See Also